Battle Ridge Builder Construction Projects

Pardue Road Bridge – Cut Bank, MT Pardue Road Bridge – Cut Bank, MT Pardue Road Bridge – Cut Bank, MT

By Battle Ridge Builders

On 12, Dec 2017 | In | By Battle Ridge Builders

Pardue Road Bridge – Cut Bank, MT

Construction of a new 85-ft single span precast prestressed bulb-tee bridge over Cut Bank Creek, with an abutment foundation of cast-in-place concrete cap, backwall and wing walls supported on driven steel piles. Remove and disposal of existing bridge, installation of detour bridge, substructure & superstructure construction, bridge railings and riprap placement.

 

 

Bowman Haley Outlet Gate Valve – Bowman, ND Bowman Haley Outlet Gate Valve – Bowman, ND

By Battle Ridge Builders

On 12, Aug 2017 | In | By Battle Ridge Builders

Bowman Haley Outlet Gate Valve – Bowman, ND

Demolish existing & provide a new butterfly gate valve, slide gate, wet well access ladder, low flow piping & cathodic protection, all 36ft below the surface. Custom designed and built lifting device to remove a 6,000lb valve.

Owner: US Army Corps of Engineers 

Red Lodge Creek Road Bridge – Red Lodge, MT Red Lodge Creek Road Bridge – Red Lodge, MT Red Lodge Creek Road Bridge – Red Lodge, MT

By Battle Ridge Builders

On 23, Jun 2017 | In | By Battle Ridge Builders

Red Lodge Creek Road Bridge – Red Lodge, MT

Removal of the existing bridge, structure excavation, installation and supply of structural backfill and riprap, supply and drive steel pile foundation, cast-in-place concrete pile caps, wingwalls & end diaphragms, supply and installation of the 78-foot single–span bulb-tee precast, prestressed concrete bridge superstructure, bridge rail & approach guardrail.

Boadle Road Bridge – Choteau, MT Boadle Road Bridge – Choteau, MT Boadle Road Bridge – Choteau, MT

By Battle Ridge Builders

On 23, Jun 2017 | In | By Battle Ridge Builders

Boadle Road Bridge – Choteau, MT

Construction of a new precast concrete bridge spanning over Pishkun Canal approximately 2 miles south of Pishkun Reservoir. The work included excavation and backfill for new abutments, PIP concrete bearing abutments, and the installation of the new 96 foot, prestressed bulb tee concrete bridge superstructure; along with the installation of ancillary work such as guardrails, riprap, approach roadwork, and traffic control measures.

Williams Bridge – Jefferson County, MT Williams Bridge – Jefferson County, MT Williams Bridge – Jefferson County, MT Williams Bridge – Jefferson County, MT Williams Bridge – Jefferson County, MT

By Battle Ridge Builders

On 23, Jun 2017 | In | By Battle Ridge Builders

Williams Bridge – Jefferson County, MT

Emergency repairs to the historic four span structure crossing the Jefferson River. The work consisted of pier stabilization, steel stringer supply and installation and riprap installation.

Beaverhead County Landfill Container Site – Dillon, MT

By Battle Ridge Builders

On 12, May 2017 | In | By Battle Ridge Builders

Beaverhead County Landfill Container Site – Dillon, MT

Complete earthwork, structural poured-in-place concrete walls and slabs, and fencing to construct a solid waste container site for Beaverhead County Landfill

Outlet Works Stilling Basin Repairs – Medicine Creek Dam, NE Outlet Works Stilling Basin Repairs – Medicine Creek Dam, NE Outlet Works Stilling Basin Repairs – Medicine Creek Dam, NE Outlet Works Stilling Basin Repairs – Medicine Creek Dam, NE

By Battle Ridge Builders

On 12, Apr 2017 | In | By Battle Ridge Builders

Outlet Works Stilling Basin Repairs – Medicine Creek Dam, NE

Remove water and control gate leakage while removing existing deteriorated concrete with hydro-demolition and waste water treatments, then furnish and place reinforced cast-in-place concrete to repair existing outlet works stilling basin.

Owner: Bureau of Reclamation 

Missoula Fire Department Boat Ramp – Missoula, MT Missoula Fire Department Boat Ramp – Missoula, MT Missoula Fire Department Boat Ramp – Missoula, MT

By Battle Ridge Builders

On 23, Mar 2017 | In | By Battle Ridge Builders

Missoula Fire Department Boat Ramp – Missoula, MT

Extension of an existing concrete boat ramp by 30 feet and associated channel and bank stabilization and re-vegetation.

Dodson South Canal Headgate Project – Dodson, MT Dodson South Canal Headgate Project – Dodson, MT Dodson South Canal Headgate Project – Dodson, MT

By Battle Ridge Builders

On 20, Dec 2016 | In | By Battle Ridge Builders

Dodson South Canal Headgate Project – Dodson, MT

Battle Ridge Builders contracted with the Malta Irrigation District for this project. The new headgate structure consists of 400+ yards of poured-in-place concrete where the 100 feet wide by 24 feet tall walls are built on footings below the water table. The project included over 5,000 yards of compacted backfill and dike construction, RipRap placement, structural steel component package fabricated in house, and head gate installation.

 

West Yellowstone Compost Facility – West Yellowstone, MT West Yellowstone Compost Facility – West Yellowstone, MT West Yellowstone Compost Facility – West Yellowstone, MT

By Battle Ridge Builders

On 23, Nov 2016 | In | By Battle Ridge Builders

West Yellowstone Compost Facility – West Yellowstone, MT

Project consisted of demolishing concrete and conveyor systems, removing over 50,000 lbs of composting equipment & trommel, repairing and repouring concrete, and installing large steel doors.